Trench Volume Calculator

Calculate excavation volume, import backfill, and spoil haul for a trench. Accounts for pipe void and soil swell.

Notes: Swell factor of 25% is typical for clay/silty soils. Sandy/granular: 10–15%. Rock: 30–40%. Import backfill volume = excavation volume minus pipe void.

Concrete Volume Calculator

Calculate concrete volume in cubic yards for slabs, walls, footings, and cylindrical structures (manholes, vaults).

Asphalt Tonnage Calculator

Calculate asphalt tonnage for pavement, patching, or trench restoration. HMA density ~145 lb/CF.

Typical densities: Dense-graded HMA: 140–150 lb/CF. SMA: 148–152 lb/CF. Open-graded: 110–120 lb/CF.

Pipe & Fittings Quantity

Calculate pipe, fittings, and bedding quantities for a pipeline. Add additional line items as needed.

Pipe Flow Calculator (Manning's Equation)

Calculate flow capacity and velocity for gravity-flow pipes: storm drains, sanitary sewer, culverts.

Manning's Equation: Q = (1/n) × A × R2/3 × S1/2 — where A = flow area, R = hydraulic radius, S = slope. Maximum hydraulic capacity occurs at ~93–94% full, not 100%.

Minimum Pipe Slope

Find the minimum slope required to maintain self-cleaning velocity (2.0 ft/s minimum, 2.5 ft/s recommended) for gravity sewer and storm drain.

ASCE Standard: Minimum 2.0 ft/s at design flow for sanitary sewer per ASCE MOP 36. Many agencies require 2.5 ft/s. Maximum velocity: 10–15 ft/s to prevent scour.

Trench Safety – OSHA Requirements

OSHA 29 CFR 1926 Subpart P sloping, benching, and shoring requirements by soil type and depth. This is a reference tool — always consult a competent person on site.

Disclaimer: This tool provides general OSHA Subpart P reference information only. All excavation safety decisions must be made by a competent person on site per OSHA 29 CFR 1926.651. Conditions vary — shoring or shielding may be required regardless of soil type.

Thrust Block Sizing

Calculate thrust force and minimum bearing area for concrete thrust blocks at pipe bends, tees, and dead ends.

Formula: T = 2 × P × A × sin(θ/2) for bends. T = P × A for dead ends and tees. Bearing area = T ÷ soil bearing capacity. Always verify with project engineer for design pressure.

Grade & Slope Calculator

Convert between percent grade, ft/ft slope, rise/run, and degrees. Calculate elevation change over a given distance.

Compaction Calculator

Calculate compaction requirements: passes needed, lift thickness, and relative compaction from Proctor test data.

Common requirements: APWA/AWWA trench backfill: 95% Standard Proctor within 3 ft of surface, 90% below. Check project specs — requirements vary by owner and pavement class.

Markup & Bid Price Calculator

Calculate bid price from direct cost using separate overhead and profit markup. Works from cost-to-bid or bid-to-cost.

Overhead vs. markup: Overhead is applied to direct cost first, then profit is applied to the overhead-loaded cost. Typical heavy civil overhead: 10–15%. Profit: 8–15% depending on risk and competition.

Unit Price Builder

Build a unit price from scratch — material, labor, equipment, subcontractor, and markup per unit of work (LF, CY, EA).

Change Order Calculator

Calculate change order value: T&M or unit price basis. Includes labor burden, equipment, materials, markup.

Production Rate Calculator

Calculate daily output, cost per unit, and project duration from crew size, hours, and production rate.

Typical production rates (heavy civil): 8" waterline in average soil: 150–300 LF/day. 8" sewer: 100–200 LF/day. Trench excavation: 300–600 LF/day. Backfill: 400–800 LF/day.

Crew Day Cost Calculator

Calculate total daily crew cost including labor, equipment, and overhead burden. Useful for T&M pricing and daily report tracking.

×
×
×
×

Construction Unit Converter

Common unit conversions for heavy civil: volume, area, weight, pressure, length.

Pipe Reference Table

Outside diameter, wall thickness, weight, and pressure class for common pipe materials used in underground utility work.

MaterialNom. Size (in)OD (in)Wall (in)Weight (lb/ft)Pressure ClassStandard

Manning's n Reference Values

Roughness coefficients for common pipe and channel materials. Use in Manning's equation for open-channel and partially-full pipe flow.

Material / Conditionn (low)n (typical)n (high)Notes
Concrete pipe (RCP)0.0110.0130.015New, good joints
PVC pipe0.0100.0120.013Smooth interior
HDPE (smooth interior)0.0090.0110.013Profile wall varies
Ductile iron pipe0.0130.0150.016New; use 0.017–0.020 for aged/tuberculated
Steel pipe0.0120.0140.017Welded; smooth interior
Corrugated metal pipe (CMP)0.0200.0240.030Standard corrugations
CMP – annular corrugated0.0220.0270.033
Vitrified clay pipe (VCP)0.0110.0130.015Good condition
Cast iron pipe0.0120.0130.015Old; increases with age
Open Channels
Concrete lined channel0.0120.0130.015Troweled finish
Riprap lined channel0.0200.0300.040Varies with D50
Earth channel – clean0.0200.0250.030Regular section
Earth channel – weedy0.0250.0350.045Light vegetation
Natural stream – clean0.0250.0300.033Straight, uniform
Natural stream – irregular0.0350.0450.060Stones, weeds
Source: Chaudhry (2008), Ven Te Chow (1959), ASCE manuals of practice. Values for design use — verify with project-specific conditions.